Furniture fixtures and equipment FF&E
FF&E refers to the procurement of furniture, fixtures and equipment.
This might be procured separately to the main construction contract (or elements of them), particularly by clients that already have systems in place for procuring fixed and loose furniture, fittings and equipment; for example schools, universities, or hospitals.
It is very important under such circumstances to define very clearly which contract every element of FF&E is within (for example, there may still be unusual or large items that it may be more sensible to procure under the main contract).
It is also important to ensure that any building work required for the installation of such items is identified and procured, that any services required (such as power or drainage) are identified and that the installation of FF&E is properly integrated into the main contract.
Requirements that affect the main contract might include:
- Built-in equipment requiring mechanical or electrical connections, such as fume cupboards or drinks stations. A description of built-in equipment should include; location, size, and requirements for power, air, water, drainage and telecommunications connection.
- Built-in equipment that does not require services such as cupboards or shelving. These should be described in terms of their location and size.
- Stand-alone loose furniture and equipment requiring services, such as washing machines, coffee machines and scanning equipment in hospitals. These should be described in terms of their location, size, and requirements for power, air, water, drainage and telecommunications connection.
- Stand-alone loose furniture and equipment not requiring services such as tables and chairs. These should be described in terms of their location and size.
It is also important that any elements that are outside of the main contract are included in the client's cost plans.
FF&E can be procured from specialist suppliers, or suppliers with whom the client already has a long term relationship. This may include maintenance arrangements. Some elements may be specially designed by FF&E designers or sourced by FF&E consultants. There is also a need for a carefully managed FF&E inventory and logistical planning to ensure items are available on-site at the right time.
In managing the procurement of FF&E, consultants take on the complicated and time-consuming task of coordinating with the design team, external vendors and internal departments for the following:
- Programming and planning.
- Sourcing.
- Project procurement strategy and risk analysis.
- Request for proposal (RFP) document development.
- RFP process management.
- Contract negotiation and buy-out.
- Order expediting and tracking.
- Installation, product acceptance and close-out.
For more information, see FF&E consultant.
[edit] Related articles in Designing Buildings
Featured articles and news
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.